The steps of a custom kitchen project, from the visit to installation
A custom kitchen project runs in five steps: visit and measurements, 3D plans and quote, a permit if needed, workshop fabrication, then site work and installation. At Ébénisterie SAM, fabrication takes 3 to 6 weeks after the plans are approved, and a turnkey kitchen is delivered 2 to 8 weeks after approval.
By Akram Samman, master cabinetmaker · Last updated:

In short: 1) visit and measurements, 2) 3D plans and quote, 3) permit if needed, 4) workshop fabrication, 5) site work and installation. You approve the plans before fabrication starts.
Step 1: the visit and measurements (week 1)
We come to your home for a free assessment visit: laser measurements and an assessment of the structure (load-bearing walls, plumbing, electrical). To get the most out of it, prepare:
- photos of your current kitchen and a few pictures of kitchens you like;
- your budget range, even a rough one;
- the list of appliances to keep or buy, with their dimensions if you know them;
- what does not work today: not enough storage, a wasted corner, an island that is too small.
Step 2: 3D plans and the quote (weeks 2 to 3)
We prepare photorealistic renderings so you can see the result, and a line-by-line quote: box and front materials, hardware, finishing panels, delivery, installation and exclusions. We bring samples of wood, veneer and lacquer; our guide solid wood, veneer or lacquer helps you choose. Nothing is built before you approve the plans.
Step 3: the permit, if needed
Replacing cabinets, counters and finishes generally does not require a permit in Montreal. You need one as soon as a load-bearing wall is opened or the sink changes place. For a turnkey project, we prepare and file the application with your borough. Details in our guide renovation permits in Montreal.
Step 4: workshop fabrication (3 to 6 weeks)
Your cabinets, island and millwork are built by our cabinetmakers in our Dorval workshop. The workshop can be visited by appointment if you want to see your kitchen being built or approve a finish.
Step 5: site work and installation
Site protection, clean demolition, work by certified trades, then installation by the cabinetmakers who built the cabinets and a final inspection. When only the cabinets are replaced, installation takes about one week. A turnkey kitchen is delivered 2 to 8 weeks after the plans are approved.
What does a typical timeline look like?
| Step | Timeline | What you do |
|---|---|---|
| Visit and measurements | Week 1 | Prepare photos, inspiration and budget |
| 3D plans and quote | Weeks 2 to 3 | Choose materials and approve the plans |
| Permit (if structure or plumbing moves) | Depends on the project | Sign the application we prepare |
| Workshop fabrication | 3 to 6 weeks | Prepare the room and order the appliances |
| Installation (cabinets only) | About 1 week | Clear the kitchen |
What can delay the schedule?
- A change of plan after approval, which means rebuilding cabinet boxes.
- A permit being needed (load-bearing wall, moved plumbing) or a sector under PIIA rules.
- A surprise behind the walls, common in older homes and plexes.
- Appliances chosen late or delivered late, when the boxes are built to their dimensions.
Ready to start? See how we build custom kitchen cabinets and our price ranges, or describe your project: we call you back the same day.